Back to catalogue

CONTAINER AVENUE / Project guides

Shipping container delivery: access and unloading

Plan the lorry route, unloading area and final position before booking. Agree who provides each service and what the site must have ready.

Separate transport, unloading, and positioning

Transport brings the container to the agreed location. Unloading removes it from the vehicle; positioning places it on the planned supports. Ask which tasks are included and who carries them out.

From the truck to your site

Plan access and placement together. These three views help you describe your site to the supplier.

Crane unloadingSide view: a truck-mounted crane with stabilisers, lifting a container from its four upper corners above the placement area.

Crane unloading

A truck-mounted crane can place the container from a suitable working area. The supplier confirms the vehicle, lifting reach and space needed for its stabilisers.

Access & manoeuvringTop view: a gate, truck, approach route and container position, with clear manoeuvring space.

Access & manoeuvring

Provide gate width, bends, slopes and obstacles. The access route must suit the selected truck, all the way to its unloading area.

Ground & door clearanceTop view: a container at its final position, with two open doors and swing arcs. A spirit level represents ground preparation.

Ground & door clearance

Prepare a stable, level position. Leave space in front of the doors for their swing and for handling goods; the supplier confirms suitable supports.

4 details to share

  • Gate and manoeuvring space
  • Ground type and stability
  • Overhead cables, branches and obstacles
  • Final position and door clearance

Illustrative diagrams, not to scale. The supplier confirms vehicle dimensions, distances and unloading method for your site.

If you have your own carrier or equipment, have its suitability checked for the actual container, weight, modifications and lifting arrangements.

Three ways to organise delivery
OptionOrganization neededPoint to resolve before booking
Pickup at depotChoice of carrier and release conditionsVehicle compatibility, loading at depot, and appointment
Transport without unloadingHandling equipment suitable on arrivalEquipment and operator available, with a time agreed between the providers
Transport with unloadingAccess and work area assessed by the providerFinal position, included work and responsibility for levelling on the supports

Lorry access for container delivery

Show the route from the road to the working area, including the usable entrance, narrow passages, turns, slopes and exit. Mark measurements and photos on a plan. Flag cables, branches, overhangs and fragile areas; the carrier assesses the route for the loaded vehicle.

  • Entrance and approach route identified.
  • Usable width at the narrowest points, gate open.
  • Heights and overhead obstacles flagged.
  • Turns, slope, and passing areas noted.
  • Route surface and known structures described.
  • Possible vehicle position and exit route drawn.

Space for unloading the container

Draw the container with its doors facing the required direction. Separately mark room for the lorry, stabilisers and handling equipment.

Describe the ground and known fill, manholes, pits, buried services and wet areas. Have the working area and final supports assessed for the proposed operation; paving alone does not establish their capacity.

Container delivery checklist

Give the full postcode, post town, building name or number and actual entrance. Add the site contact, delivery restrictions and known container identity, weight and modifications.

List equipment already on site, tasks assigned to each provider and preparation still outstanding.

Who prepares and who approves?
ItemInformation to provideWhat needs to be confirmed
ContainerModel, modifications, and actual specifications availableContainer identified and suitable for the planned handling
RoutePlan, measurements, photos, and constraintsPossible route and manoeuvres with the chosen vehicle
Ground and supportsSoil condition, work needed, and container placementSuitable preparation by the relevant professionals
OperationParties involved, equipment, and responsibilitiesWritten description of the work and the conditions for carrying it out

Make sure everything is ready before you set the date

Resolve access, ground or equipment questions before confirming the date; the carrier may need a visit. Check the quote for transport, unloading, placement, taxes and any extra services, including the responsibilities of each provider.

Organise the delivery day

Clear the agreed areas and make the site contact available. Report changed ground conditions, trenches, obstacles or a different placement position before work starts.

Follow the operator’s instructions and keep out of the handling area. Do not guide the suspended load by hand, go underneath it or improvise a lift. If the agreed plan cannot be followed, stop and have the provider reassess it.

Check the container once it's in place

Approach only when the operator says it is safe. Compare the number, visible condition, repairs and equipment with the offer. Check orientation and door operation once the container is on its supports.

Photograph differences and report them under the agreed terms. A sticking door needs investigation: the cause may be the positioning, the container or handling. Keep the offer, communications and delivery record together.

Checklist before the truck leaves

  • Actual entrance, full address and site contact.
  • Measured route and photos, with overhead obstacles marked.
  • Container identity, weight and modifications where known.
  • Separate lorry work area and final placement position.
  • Ground, buried services and supports assessed for the operation.
  • Providers, unloading method, services and date agreed.
  • Recent changes reported and receipt documents ready.

Find the right type of container

Technical references

Key points

  • Show the full truck route and the unloading area.
  • Agree who unloads, places and levels the container.
  • Report changes to the site before the truck leaves.